How was Burj Khalifa built, and how long did it take?

The short answer

Burj Khalifa took about six years to build. Construction started in 2004, the tower topped out in January 2009 according to secondary sources, and it opened on 4 January 2010. A joint venture led by Samsung C&T built it, with between 7,000 and 12,000 workers on site at different stages, according to news reports. Checked 9 October 2026.

Key facts

Construction start
2004 (CTBUH). Exact day differs between sources: 6 or 12 January 2004.
Topped out
17 January 2009 (secondary sources)
Opened
4 January 2010
Main contractor
Samsung C&T, with Besix and Arabtec
Workers on site
About 7,000 (The National, late 2008) to 12,000 at peak (AP, 2010)
Concrete pumped
To about 606 m, reported as a record (Putzmeister, via search summaries; no Guinness listing found)
Glass panels
About 26,000 (Guinness World Records; BNP Media, 2010)

What were the main construction dates?

Burj Khalifa construction timeline
WhenWhat happenedSourceConfidence
2004Construction starts (day given as 6 or 12 January)CTBUH; WikipediaHigh for year, low for day
December 2004Samsung named main contractorGulf News, 9 December 2004High
July 2007Tallest building in the world under construction, at over 636 mThe NationalMedium
17 January 2009Tower tops outWikipedia (secondary)Medium
1 October 2009Exterior complete, per an Emaar announcementWikipedia (secondary)Medium
4 January 2010Official opening; renamed from Burj DubaiAssociated Press, 4 January 2010High

How many people built Burj Khalifa?

Figures depend on the date. The National reported about 7,000 workers on site around the clock in late 2008. The Associated Press and a Samsung official quoted by the Korea Times (19 May 2011) gave up to 12,000 at peak, mainly from India and Bangladesh, with about 160 specialists from the US, the UK and Germany.

How much concrete and steel went into it?

Materials and records, with the source for each
ItemFigureSource
Concrete strength100 MPa (14,500 psi)BNP Media, August 2010
Concrete volumeAbout 330,000 m3BNP Media (over 430,000 cubic yards); Wikipedia (330,000 m3)
Reinforcing steel43,000 tons (BNP Media) or 55,000 tonnes (Wikipedia)Sources differ
FoundationA raft about 3.7 m thick on 192 or 194 piles (sources differ)BNP Media; Wikipedia
Concrete pumping height606 m, a record at the timePutzmeister
Glass panelsAbout 26,000Guinness World Records; BNP Media

Where two figures are shown, the sources disagree and we have not found a primary figure.

How was the spire put on top?

The steel spire was assembled inside the top of the tower and pushed up with hydraulic jacks, according to the Skyscraper Museum and BNP Media (August 2010). The official site says the spire uses over 4,000 tonnes of steel and was jacked up over 200 m. See Burj Khalifa height and floors.

What made the build difficult?

Trade press named three problems: the height grew from about 700 m at the competition stage (818 m in one report, 828 m as built), concrete had to be pumped to record heights in Dubai's heat, and wind had to be managed on a tower that tall. The 2008 credit crisis also hit suppliers. Wind is covered on the architecture and structure page.

Common questions

How long did it take to build Burj Khalifa?

About six years. Construction started in 2004 and the tower opened on 4 January 2010.

Who built Burj Khalifa?

Samsung C&T of South Korea was the main contractor, in a joint venture with Besix of Belgium and Arabtec of the UAE. Emaar Properties was the developer.

How many workers built Burj Khalifa?

Reports give about 7,000 workers on site in late 2008 and up to 12,000 at peak, according to The National and the Associated Press.

Sources

  1. Skyscraper Center (Council on Tall Buildings and Urban Habitat), Burj Khalifa building page, read on 8 October 2026
  2. Gulf News, "Samsung is main contractor to build Burj Dubai", 9 December 2004
  3. Burj Khalifa official site, structures page, read on 8 October 2026
  4. Wikipedia, "Burj Khalifa" (secondary source, used where no primary figure was found), read on 8 October 2026
  5. The National, "Burj Dubai moves closer to completion" (late 2008)
  6. Associated Press via HeraldNet, "Dubai names tallest tower after bailout patron", 4 January 2010
  7. Korea Times, Samsung C&T on Burj Khalifa, 19 May 2011
  8. BNP Media and Engineered Systems, "Beyond Limits", August 2010
  9. Putzmeister, Burj Khalifa project story, read on 9 October 2026
  10. Skyscraper Museum, Burj Khalifa spire note, read on 9 October 2026
  11. Guinness World Records, Burj Khalifa icon page (inducted 2024), read on 9 October 2026
Ask

Ask a question about the tower

One message is enough. We reply by WhatsApp, phone or email, and there is no pressure to book anything.

Prefer WhatsApp?Message us on WhatsApp

We use your details only to answer you and do not sell them. See the privacy policy.

Or use WhatsApp